BUILDER

Abh Developers Private Limited

Type CompanyRERA projects 7Districts Nashik
BUILDER THOK
Ruko
2 of 2projects with possession moved
18 moaverage extension when late
0lapsed registrations
7MahaRERA projects · 5 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Treeland Phase - 1
Nashik (M Corp.)
Apr 2024Apr 2025
12 mo
Apr 2025Apr 2027
24 mo
Treeland - Phase 4
Nashik (M Corp.)
——
—
Treeland Phase-2
Nashik (M Corp.)
——
—
Aangan
Aanandwali
——
—
Treeland Phase-5
Nashik (M Corp.)
——
—
Treeland Phase - 3
Nashik (M Corp.)
——
—

Signals from filings & records

Verification in progressMahaRERA

2 of 7 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Treeland Phase - 1
P51600025058 · Nashik (M Corp.)
Ruko
Abh Nature Tales
P51600053268 · Nashik
Dhyaan Do
Treeland - Phase 4
P51600029154 · Nashik (M Corp.)
Not scored
Treeland Phase-2
P51600034705 · Nashik (M Corp.)
Not scored
Aangan
P51600046755 · Aanandwali
Not scored
Treeland Phase-5
P51600034430 · Nashik (M Corp.)
Not scored
Treeland Phase - 3
P51600025197 · Nashik (M Corp.)
Not scored