Adarsh Infra Developers

Type Firm / individualRERA projects 1Districts Thane
BUILDER THOK
Ruko
1 of 1projects with possession moved
62 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Uma Residency, Phase I
Khardi (ct) · lapsed
Jun 2021Aug 2026
62 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Uma Residency, Phase I
P51700011302 · Khardi (ct)