BUILDER

Agn Venture

Type Firm / individualRERA projects 3Districts Pune
BUILDER THOK
Dhyaan Do
1 of 3projects with possession moved
4 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2024Dec 2024
not moved
Dec 2026Dec 2026
not moved
Dec 2027Apr 2028
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

The Mpire Phase III
P52100032906 · Haveli
Ruko
The Mpire Building E
P52100050878 · Haveli
Pakka
The Mpire Building - F
P52100077527 · Haveli
Pakka