BUILDER

Aims Golf Town Developers Private Limited

Type CompanyRERA projects 4Districts Gautam Buddha Nagar
BUILDER THOK
Ruko
2 of 3projects with possession moved
15 moaverage extension when late
0lapsed registrations
4UP RERA projects

Delivery track record

Possession date first declared vs latest on UP RERA
PROJECTPROMISEDLATESTMOVED BY
Aims Green Avenue (Phase-1)
Gautam Buddha Nagar
Dec 2018Dec 2018
not moved
Aims Green Avenue (Phase-2)
Gautam Buddha Nagar
Jun 2019Dec 2020
18 mo
Aims Green Aenue (Phase-3)
Gautam Buddha Nagar
Dec 2019Dec 2020
12 mo
1 more project is being verified or has no declared dates yet.

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Aims Green Avenue (Phase-1)
UPRERAPRJ7473 · Gautam Buddha Nagar
Dhyaan Do
Aims Green Avenue (Phase-2)
UPRERAPRJ7136 · Gautam Buddha Nagar
Ruko
Aims Green Aenue (Phase-3)
UPRERAPRJ7262 · Gautam Buddha Nagar
Ruko
Aims Windsor Street
UPRERAPRJ10867 · Gautam Buddha Nagar
Ruko