Type Firm / individualRERA projects 2Districts Mumbai City
BUILDER THOK
Ruko
2 of 2projects with possession moved
24 moaverage extension when late
2lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Ndw The Crest
E-400008 · lapsed
Dec 2022Dec 2025
36 mo
Vipin Residency
E-400008 · lapsed
Dec 2022Dec 2023
12 mo

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Ndw The Crest
P51900007311 · E-400008
Ruko
Vipin Residency
P51900006333 · E-400008
Ruko