BUILDER

Arihant Superstructures Limited

Type CompanyRERA projects 15Districts Raigarh, Thane
BUILDER THOK
Dhyaan Do
12 of 15projects with possession moved
9 moaverage extension when late
0lapsed registrations
15MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Arihant Arshiya Phase II
Dahivali Tarf Boreti
Mar 2019Sept 2020
18 mo
Apr 2019Oct 2020
18 mo
Arihant Arshiya Phase III
Dahivali Tarf Boreti
Sept 2020Sept 2020
not moved
Dec 2024Dec 2024
not moved
4anaika
Koyana Velhe
Dec 2027Dec 2027
not moved
Mar 2029Jul 2029
4 mo
Mar 2030Apr 2033
37 mo
Mar 2030Jul 2030
4 mo
Mar 2030Jul 2030
4 mo
Dec 2030Apr 2031
4 mo
Dec 2030Apr 2031
4 mo
Dec 2030Apr 2031
4 mo
Dec 2031Apr 2032
4 mo
Dec 2031Apr 2032
4 mo
Dec 2031Apr 2032
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Arihant Arshiya Phase II
P52000002342 · Dahivali Tarf Boreti
Ruko
Arihant Aarohi Phase I
P51700004679 · Thane
Ruko
Arihant Arshiya Phase III
P52000003422 · Dahivali Tarf Boreti
Ruko
Arihant Aarohi Phase II
P51700015328 · Thane
Ruko
4anaika
P52000022982 · Koyana Velhe
Pakka
Arihant Aaradhya Phase I
P51700045430 · Bhiwandi
Pakka
Arihant Adarsh Phase I
P52000045699 · Panvel
Ruko
Arihant Aakarshan Phase I
P52000034793 · Panvel
Pakka
World Villas Phase 1
P52000076635 · Khalapur
Pakka
Arihant Aayan Phase I
P51700049910 · Kalyan
Pakka
Arihant Aaradhya Phase II
P51700049981 · Bhiwandi
Pakka
Arihant Arshiya Phase IV
P52000056037 · Khalapur
Pakka