BUILDER

Arihant Vastushilp Propcon Private Limited

Type CompanyRERA projects 1Districts Pune
BUILDER THOK
Ruko
1 of 1projects with possession moved
66 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Elegant Residency Phase II
Pimpri Chinchawad (M Corp.) · lapsed
Mar 2019Sept 2024
66 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Elegant Residency Phase II
P52100009324 · Pimpri Chinchawad (M Corp.)
Ruko