Ashiana Housing Limited

Type CompanyRERA projects 8Districts Pune
BUILDER THOK
Pakka
4 of 5projects with possession moved
4 moaverage extension when late
0lapsed registrations
8MahaRERA projects · 3 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Oct 2026Oct 2026
not moved
Mar 2027Jul 2027
4 mo
Mar 2028Jul 2028
4 mo
Sept 2029Jan 2030
4 mo
Mar 2030Jul 2030
4 mo
3 more projects are being verified or have no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

5 of 8 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Ashiana Malhar Phase I And Commercial Block
P52100046049 · Mulshi
Pakka
Ashiana Amodh Phase I
P52100050979 · Mawal
Pakka
Ashiana Malhar Phase III
P52100076601 · Mulshi
Pakka
Ashiana Malhar Phase 4
PR1260002501981 · Mulshi
Pakka
Ashiana Amodh Phase 3
PR1260002502470 · Mawal
Pakka
Ashiana Malhar Phase II
P52100052593 · Mulshi
Not scored
Niwas
P52100054148 · Mulshi
Not scored
Ashiana Amodh Phase II
P52100056484 · Mawal
Not scored