BUILDER

Atharvashree Buildmat Private Limited

Type CompanyRERA projects 6Districts Nashik
BUILDER THOK
Ruko
3 of 6projects with possession moved
18 moaverage extension when late
0lapsed registrations
6MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2021Dec 2021
not moved
Dec 2023Dec 2023
not moved
Dec 2023Dec 2026
36 mo
Dec 2024Dec 2024
not moved
Dec 2024Jun 2025
6 mo
Dec 2025Dec 2026
12 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Shree Atharv Park Phase-i
P51600018505 · Nashik
Ruko
Shree Atharv Park Phase-ii
P51600018359 · Nashik
Ruko
Shree Atharvapark 2 Phase 1
P51600031337 · Nashik
Ruko
Shree Atharv Park Phase-iii
P51600021832 · Nashik
Ruko
Shree Atharvapark 2 Phase 2
P51600031143 · Nashik
Ruko
Shree Atharv Park Phase-iv
P51600021846 · Nashik
Dhyaan Do