Avinash Jaywant Durgade

Type Firm / individualRERA projects 2Districts Pune
BUILDER THOK
Ruko
2 of 2projects with possession moved
4 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Herambh Elite
Mulshi · lapsed
Mar 2026Jul 2026
4 mo
Dec 2026Apr 2027
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements