BUILDER

Bhuvi Landmarks LLP

Type LLPRERA projects 10Districts Aurangabad, Jalna
BUILDER THOK
Ruko
2 of 5projects with possession moved
15 moaverage extension when late
1lapsed registrations
10MahaRERA projects · 5 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2018Dec 2019
12 mo
Krishnaban Phase 2
Jalna (M Cl)
Mar 2019Sept 2020
18 mo
Bhuvi Gharkul
Aurangabad (M Corp.)
Dec 2021Dec 2021
on time
Bhuvi Madhuban
Hirapur · lapsed
May 2023May 2023
on time
Jul 2024Jul 2024
on time
Shubh Labh Heights
Aurangabad (M Corp.)
——
—
——
—
Krishnaban Phase 1
Jalna (M Cl)
——
—
——
—
——
—

Signals from filings & records

Verification in progressMahaRERA

5 of 10 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Bhuvi Madhurban
P51500002962 · Balapur
Ruko
Krishnaban Phase 2
P51400011318 · Jalna (M Cl)
Ruko
Bhuvi Gharkul
P51500014339 · Aurangabad (M Corp.)
Ruko
Bhuvi Madhuban
P51500020977 · Hirapur
Ruko
Bhuvi Madhurban Phase-2
P51500021822 · Aurangabad
Ruko
Shubh Labh Heights
P51500026771 · Aurangabad (M Corp.)
Not scored
Bhuvi Vrundavan - 1
P51500003772 · Kubhephal
Not scored
Krishnaban Phase 1
P51400006388 · Jalna (M Cl)
Not scored
Bhuvi Vishwaban
P51500020149 · Hirapur
Not scored
Bhuvi Vishwaban Phase-2
P51500022135 · Aurangabad
Not scored