BUILDER
Celerity Infrastructure Private Limited
BUILDER THOK
Dhyaan Do
1 of 2projects with possession moved
6 moaverage extension when late
0lapsed registrations
2UP RERA projects
Delivery track record
Possession date first declared vs latest on UP RERA
PROJECTPROMISEDLATESTMOVED BY
ATS Pristine Golf Villas ( Phase -1 )
Dec 2022Jun 2023Plot No. Sc-01/c, C-a2, A4, A6, A11, & A12, Sector 150, Noida, Gautam Budh Nagar, UP
6 mo
ATS Kingston Heath
Aug 2026Aug 2026Plot No. Sc-01/c, C-a2, A4, A6, A11, & A12, Sector 150, Noida, Gautam Budh Nagar, UP
not moved
Signals from filings & records
No approved insolvency matchIBBI
No IBBI announcement has been matched to this builder after review.
IBBI public announcements
Projects
ATS Pristine Golf Villas ( Phase -1 )
UPRERAPRJ3796 · Plot No. Sc-01/c, C-a2, A4, A6, A11, & A12, Sector 150, Noida, Gautam Budh Nagar, UP
ATS Kingston Heath
UPRERAPRJ180413 · Plot No. Sc-01/c, C-a2, A4, A6, A11, & A12, Sector 150, Noida, Gautam Budh Nagar, UP