BUILDER

Cosmic Infrastructure

Type Firm / individualRERA projects 1Districts Pune
BUILDER THOK
Ruko
1 of 1projects with possession moved
29 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Pentagon Business Hub
Pimpri Chinchawad (M Corp.) · lapsed
Apr 2024Sept 2026
29 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Pentagon Business Hub
P52100034525 · Pimpri Chinchawad (M Corp.)
Ruko