BUILDER

Crystal Constructions

Type Firm / individualRERA projects 3Districts Mumbai Suburban
BUILDER THOK
Ruko
2 of 3projects with possession moved
27 moaverage extension when late
3lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sky Heights
Borivali · lapsed
Dec 2021Dec 2021
lapsed
Crystal Heights
Andheri · lapsed
Jul 2022Dec 2025
41 mo
Dec 2022Dec 2023
12 mo

Signals from filings & records

3 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Sky Heights
P51800011325 · Borivali
Ruko
Crystal Heights
P51800003672 · Andheri
Ruko
Sky Heights Phase II Wing D And E
P51800014393 · Borivali
Ruko