BUILDER

Digamber Parulekar

Type Firm / individualRERA projects 7Districts Pune
BUILDER THOK
Ruko
3 of 4projects with possession moved
4 moaverage extension when late
1lapsed registrations
7MahaRERA projects · 3 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sadashanti
Kothrud
Mar 2022Mar 2022
not moved
Kalpak
Gultekadi · lapsed
Jun 2022Nov 2022
5 mo
Dec 2024Mar 2025
3 mo
Pradnyesh
Haveli
Dec 2027Apr 2028
4 mo
3 more projects are being verified or have no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

4 of 7 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Sadashanti
P52100020351 · Kothrud
Ruko
Kalpak
P52100026027 · Gultekadi
Ruko
Suhas Sudhanva
P52100030693 · Kothrud
Ruko
Pradnyesh
P52100077494 · Haveli
Pakka
Nav Nirmal
P52100003211 · Kothrud
Not scored
Dhanwantari Terrace Cooperative Housing Society Limited
P52100005496 · Kothrud
Not scored
Blossom
P52100030039 · Haveli
Not scored