Dilip Baburao Tupe

Type Firm / individualRERA projects 4Districts Pune
BUILDER THOK
Pakka
2 of 2projects with possession moved
7 moaverage extension when late
0lapsed registrations
4MahaRERA projects · 2 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Aquila
Haveli
Mar 2028Jan 2029
10 mo
Astrana
Haveli
Mar 2028Jul 2028
4 mo
2 more projects are being verified or have no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

2 of 4 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Aquila
P52100080347 · Haveli
Dhyaan Do
Astrana
P52100055666 · Haveli
Pakka
Stella
P52100080288 · Haveli
Not scored
Freedom High Street
P52100055913 · Haveli
Not scored