BUILDER

Ellora Buildwell PVT LTD

Type CompanyRERA projects 5Districts Pune
BUILDER THOK
Dhyaan Do
3 of 5projects with possession moved
13 moaverage extension when late
0lapsed registrations
5MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Nakshatra I-land - 1
Pimpri Chinchawad (M Corp.)
Jul 2019Jan 2021
18 mo
Jun 2026Jun 2026
not moved
Dec 2026Apr 2028
16 mo
Dec 2027Apr 2028
4 mo
Jul 2029Jul 2029
not moved

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Nakshatra I-land - 1
P52100003804 · Pimpri Chinchawad (M Corp.)
Ruko
Nakshatra I Land Phase 3
P52100046609 · Haveli
Pakka
Nakshatra I Land Phase 5
P52100050468 · Haveli
Dhyaan Do
Nakshatra I Land Phase - 7
P52100056189 · Haveli
Pakka
Nakshatra I Land – Phase 8
PC1264042602061 · Haveli
Pakka