Gurumauli Vihar

Type Firm / individualRERA projects 1Districts Pune
BUILDER THOK
Ruko
1 of 1projects with possession moved
18 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Gurumauli Vihar
Baner · lapsed
May 2019Nov 2020
18 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Gurumauli Vihar
P52100006648 · Baner