BUILDER

Heramb Builders & Developers

Type Firm / individualRERA projects 3Districts Satara, Kolhapur
BUILDER THOK
Ruko
1 of 1projects with possession moved
12 moaverage extension when late
1lapsed registrations
3MahaRERA projects · 2 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Heramb Vastu
Nune · lapsed
Dec 2020Dec 2021
12 mo
2 more projects are being verified or have no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

1 of 3 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Heramb Vastu
P52700010656 · Nune
Ruko
Mayur Vihar Apartment
P53000013377 · Gadhinglaj
Not scored
Heramb Park
P52700034010 · Satara
Not scored