BUILDER

Honest Developers

Type Firm / individualRERA projects 2Districts Thane
BUILDER THOK
Ruko
1 of 1projects with possession moved
17 moaverage extension when late
1lapsed registrations
2MahaRERA projects · 1 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Kalyan Nagari
Kon (ct) · lapsed
Oct 2022Mar 2024
17 mo
Kalyan Vihar
Bhiwandi
——
—

Signals from filings & records

Verification in progressMahaRERA

1 of 2 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Kalyan Nagari
P51700016054 · Kon (ct)
Ruko
Kalyan Vihar
P51700033988 · Bhiwandi
Not scored