Type Firm / individualRERA projects 3Districts Pune, Kolhapur
BUILDER THOK
Ruko
1 of 1projects with possession moved
12 moaverage extension when late
1lapsed registrations
3MahaRERA projects · 2 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Gayatri Mantra
Pimpri Chinchawad (M Corp.) · lapsed
Mar 2020Mar 2021
12 mo
Nandanwan
Kolhapur (M Corp.)
——
—
——
—

Signals from filings & records

Verification in progressMahaRERA

1 of 3 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Gayatri Mantra
P52100015674 · Pimpri Chinchawad (M Corp.)
Ruko
Nandanwan
P53000020937 · Kolhapur (M Corp.)
Not scored
Manorama Sankul
P53000052199 · Karvir
Not scored