Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Balaji Vishwa Building C
Pune (M Corp.) · lapsed
Jun 2021Dec 2022
18 mo
Dec 2028Apr 2029
4 mo
2 more projects are being verified or have no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

2 of 4 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Balaji Vishwa Building C
P52100004239 · Pune (M Corp.)
Ruko
Ideal Elite
PR1150002502143 · Karvir
Pakka
Balaji Vishwa Building D And E
P52100028409 · Haveli
Not scored
Dmellos Residency
P99000025569 · Vasai-virar City (M Corp)
Not scored