6 of 8projects with possession moved
6 moaverage extension when late
0lapsed registrations
11MahaRERA projects · 3 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2027Apr 2028
4 mo
Dec 2028Apr 2029
4 mo
Dec 2028Dec 2028
on time
Dec 2028Apr 2030
16 mo
Dec 2028Apr 2029
4 mo
Oct 2029Feb 2030
4 mo
Dec 2029Dec 2029
on time
Mar 2032Jul 2032
4 mo
——
—

Signals from filings & records

Verification in progressMahaRERA

8 of 11 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Kohinoor Kaleido
P52100046027 · Haveli
Pakka
Kohinoor Central Park - Phase 1
P52100056358 · Mulshi
Pakka
Kohinoor Riverdale
P52100056021 · Haveli
Pakka
Kohinoor Satori Mahalunge
P52100066472 · Mulshi
Dhyaan Do
Kohinoor Riverdale - Phase II
P52100079217 · Haveli
Pakka
Kohinoor Kaleido-phase-ii
P52100078107 · Haveli
Pakka
Kohinoor Woodshire
P52100078709 · Mulshi
Pakka
Kohinoor Avantara
PR1260002501984 · Mulshi
Pakka
Kohinoor Woodshire Phase 2
PR1261012501461 · Mulshi
Not scored
Kohinoor Royale Towers
PR1260002501033 · Mulshi
Not scored
Kohinoor Central Park - Phase II
P52100078767 · Mulshi
Not scored