3 of 4projects with possession moved
9 moaverage extension when late
1lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Monika Residency
Panvel · lapsed
Jun 2024Dec 2025
18 mo
May 2027Sept 2027
4 mo
May 2028Sept 2028
4 mo
May 2029May 2029
not moved

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Monika Residency
P52000028412 · Panvel
Ruko
Janki Park Building No 3
P99000078780 · Palghar
Pakka
Janki Park Building No. 2
P99000079925 · Palghar
Pakka
Jankrishna Heights
PR1330002601758 · Ambarnath
Pakka