BUILDER

Jm Developers

Type Firm / individualRERA projects 3Districts Raigarh
BUILDER THOK
Ruko
2 of 3projects with possession moved
20 moaverage extension when late
1lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2021Dec 2021
not moved
Dec 2023Dec 2025
24 mo
Dec 2024Mar 2026
15 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Bay View Residency Phase 2 Bldg 3
P52000006354 · Tupgaon
Ruko
Bay View Residency Phase 3 Bldg 4
P52000005770 · Tupgaon
Ruko
Bay View Residency Phase 4 Bldg 5
P52000050697 · Khalapur
Ruko