BUILDER

Kamalraj Realtors

Type Firm / individualRERA projects 7Districts Pune
BUILDER THOK
Ruko
1 of 1projects with possession moved
23 moaverage extension when late
0lapsed registrations
7MahaRERA projects · 6 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Nov 2018Oct 2020
23 mo
——
—
——
—

Signals from filings & records

Verification in progressMahaRERA

1 of 7 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Kamalraj Nishigandh B And C Building
P52100001887 · Dighi
Ruko
Kamalraj Indradhanu A Building
PR1260002600879 · Haveli
Not scored
Kamalraj Pasaydan
P52100001694 · Dighi
Not scored
Kamalraj Pasaydan C Building
P52100017484 · Haveli
Not scored
Kamalraj Pasaydan D Building
P52100019182 · Haveli
Not scored
Kamalraj Nishigandh A Comm Residential MHADA
P52100029675 · Dighi
Not scored
Kamalraj Devgiri
P52100031738 · Dighi
Not scored