BUILDER

Kbc Global Limited

Type CompanyRERA projects 15Districts Nashik
BUILDER THOK
Ruko
7 of 8projects with possession moved
40 moaverage extension when late
8lapsed registrations
15MahaRERA projects · 7 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Hari Vishwa D Building
Nashik · lapsed
Dec 2019Aug 2023
44 mo
Hari Kunj Mayflower
Nashik · lapsed
Mar 2021Dec 2023
33 mo
Hari Bhakti
Deolali (cb) · lapsed
Jun 2021Dec 2024
42 mo
Hari Aakruti Phase II
Nashik · lapsed
Jun 2021Jul 2026
61 mo
Hari Vruddhi
Deolaligaon · lapsed
Dec 2021Dec 2025
48 mo
Hari Sanskruti Phase II
Deolaligaon · lapsed
Aug 2022Aug 2024
24 mo
Hari Krishna Phase IV
Nashik · lapsed
Nov 2023Dec 2025
25 mo
Hari Laxmi Phase II
Vihitgaon · lapsed
Dec 2024Dec 2024
on time
——
—
Hari Naman
Deolaligaon
——
—
——
—
Hari Sparsh II
Bhagur Rural
——
—
——
—
——
—
——
—

Signals from filings & records

Verification in progressMahaRERA

8 of 15 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
8 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Hari Vishwa D Building
P51600001205 · Nashik
Ruko
Hari Kunj Mayflower
P51600020249 · Nashik
Ruko
Hari Bhakti
P51600000585 · Deolali (cb)
Ruko
Hari Aakruti Phase II
P51600014676 · Nashik
Ruko
Hari Vruddhi
P51600018377 · Deolaligaon
Ruko
Hari Sanskruti Phase II
P51600000551 · Deolaligaon
Ruko
Hari Krishna Phase IV
P51600020324 · Nashik
Ruko
Hari Laxmi Phase II
P51600005165 · Vihitgaon
Ruko
Hari Vatika
P51600000220 · Sansari
Not scored
Hari Naman
P51600000228 · Deolaligaon
Not scored
Hari Sparsh Phase III
P51600000225 · Bhagur Rural
Not scored
Hari Sparsh II
P51600000119 · Bhagur Rural
Not scored