3 of 4projects with possession moved
31 moaverage extension when late
1lapsed registrations
21MahaRERA projects · 17 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jun 2021Dec 2022
18 mo
Dec 2021Dec 2027
72 mo
Dec 2022Dec 2022
on time
Apr 2030Aug 2030
4 mo
Yazarina One
Fnorth-400014
——
—
——
—
Yazarina III
Ward Fnorth
——
—
——
—
——
—
——
—
——
—

Signals from filings & records

Verification in progressMahaRERA

4 of 21 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Eaze Zone In Laxmi Singh Complex
P51800011978 · Borivali
Ruko
Rustomjee Summit
P51800003590 · Borivali
Ruko
Rustomjee Seasons - Wing A
P51800001433 · Andheri
Ruko
Rustomjee Balmoral - Wing D
P51800079955 · Kurla
Pakka
Rustomjee Balmoral - Wing C
PR1180002502115 · Kurla
Not scored
Rustomjee Balmoral - Wing A
P51800080624 · Kurla
Not scored
Rustomjee Balmoral - Wing F
P51800080027 · Kurla
Not scored
Rustomjee Seasons - Wing B
P51800000605 · Andheri
Not scored
Rustomjee Seasons - Wing C
P51800000309 · Andheri
Not scored
Yazarina One
P51900000287 · Fnorth-400014
Not scored
Rustomjee Pinnacle
P51800006915 · Borivali
Not scored
Rustomjee Paramount - Wing C
P51800000481 · Andheri
Not scored