BUILDER

Kushal Adiraj Associates

Type Firm / individualRERA projects 2Districts Pune
BUILDER THOK
Ruko
1 of 2projects with possession moved
30 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Kushal Swarnali C4
Kharabwadi (ct)
Dec 2019Jun 2022
30 mo
Kushal Swarnali C1
Kharabwadi (ct) · lapsed
Dec 2021Dec 2021
lapsed

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Kushal Swarnali C4
P52100004813 · Kharabwadi (ct)
Ruko
Kushal Swarnali C1
P52100016192 · Kharabwadi (ct)
Ruko