BUILDER

M S Builders And Developers

Type Firm / individualRERA projects 3Districts Pune, Sangli, Nashik
BUILDER THOK
Dhyaan Do
1 of 3projects with possession moved
4 moaverage extension when late
1lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
M S Plaza
Mulshi · lapsed
Dec 2022Dec 2022
lapsed
Apr 2026Apr 2026
not moved
Dec 2026Apr 2027
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

M S Plaza
P52100022956 · Mulshi
Ruko
Shalinee Heights
P53100051974 · Miraj
Pakka
Tanishq Park Royals
P51600055929 · Nashik
Pakka