BUILDER

M/s. Flynirvanna Builder LLP

Type LLPRERA projects 3Districts Pune
BUILDER THOK
Ruko
3 of 3projects with possession moved
38 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Essenciya
Haveli
Mar 2024Oct 2027
43 mo
Valenciya
Haveli
Apr 2024Oct 2027
42 mo
Artmeciya
Haveli
Dec 2026Apr 2029
28 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Essenciya
P52100032828 · Haveli
Ruko
Valenciya
P52100033005 · Haveli
Ruko
Artmeciya
P52100080933 · Haveli
Ruko