BUILDER

M/s. J.k. Infrastructure

Type Firm / individualRERA projects 1Districts Kolhapur
BUILDER THOK
Ruko
1 of 1projects with possession moved
82 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dwarka Heights Phase II
Kolhapur (M Corp.) · lapsed
Dec 2019Oct 2026
82 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements