BUILDER
M/s. Kamla Homes & Infrastructure
BUILDER THOK
Ruko
2 of 2projects with possession moved
12 moaverage extension when late
1lapsed registrations
2MahaRERA projects
Delivery track record
Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Kamla Jainson Phase 1 Part Podium From 2nd To 4th Floor And 5th To 25th Habitable Floors
Dec 2022Dec 2023Borivali · lapsed
12 mo
Signals from filings & records
1 project lapsed on MahaRERAMahaRERA
Registration lapsed without completion being recorded.
MahaRERA registration
No approved insolvency matchIBBI
No IBBI announcement has been matched to this builder after review.
IBBI public announcements
Projects
Kamla Jainson Phase 1 Part Podium From 2nd To 4th Floor And 5th To 25th Habitable Floors
P51800014629 · Borivali
Kamla Jainson Wing C
P51800052711 · Borivali