Type Firm / individualRERA projects 2Districts Palghar, Aurangabad
BUILDER THOK
Ruko
0 of 2projects with possession moved
0 moaverage extension when late
0lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Rajhans Kshitij Iris Wing E F G
Vasai-virar City (M Corp)
Dec 2018Dec 2018
not moved
Pragati Phase III
Aurangabad (M Corp.)
Dec 2019Dec 2019
not moved

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Rajhans Kshitij Iris Wing E F G
P99000003532 · Vasai-virar City (M Corp)
Ruko
Pragati Phase III
P51500012353 · Aurangabad (M Corp.)
Ruko