BUILDER
Madhukara Real Estate
BUILDER THOK
Dhyaan Do
—projects with possession moved
—average extension when late
1lapsed registrations
4HRERA projects
Delivery track record
Possession date first declared vs latest on HRERA
No project with both possession dates yet.
4 more projects are being verified or have no declared dates yet.
Signals from filings & records
1 project lapsed on HRERAHRERA
Registration lapsed without completion being recorded.
HRERA registration
No approved insolvency matchIBBI
No IBBI announcement has been matched to this builder after review.
IBBI public announcements
Projects
Green City
RERA-PKL-1364-2023 · Sector 2 Narwana
Green Valley
RERA-PKL-1094-2022 · Village Haibatpur Sector 11
Highway Green City
RERA-PKL-1299-2023 · Village Haibatpur Sector 26A
Highway Green's
RERA-PKL-1175-2022 · Village Habatpur Sector 26A