BUILDER

Maitri Associates

Type Firm / individualRERA projects 4Districts Pune, Kolhapur, Mumbai City
BUILDER THOK
Ruko
1 of 4projects with possession moved
13 moaverage extension when late
1lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Maitri Aarambh
Haveli · lapsed
Dec 2023Dec 2023
lapsed
Dec 2024Dec 2024
not moved
Dosti Mezzo 22
Ward Fnorth
Jun 2026Jul 2027
13 mo
Dec 2026Dec 2026
not moved

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Maitri Aarambh
P52100020902 · Haveli
Ruko
Shree Mahalaxmi Villas Phase-i
P53000022207 · Karvir
Ruko
Dosti Mezzo 22
P51900026976 · Ward Fnorth
Dhyaan Do
Shree Mahalaxmi Villas Phase-2
P53000052615 · Karvir
Pakka