Maple City Developers

Type Firm / individualRERA projects 3Districts Pune
BUILDER THOK
Ruko
1 of 3projects with possession moved
52 moaverage extension when late
2lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Aapla Ghar Talegaon Dhamdhere Phase I
Talegaon Dhamdhere · lapsed
Dec 2021Dec 2021
lapsed
Dec 2022Apr 2027
52 mo
Dec 2023Dec 2023
lapsed

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.