BUILDER

Marne Group

Type Firm / individualRERA projects 2Districts Pune
BUILDER THOK
Ruko
1 of 2projects with possession moved
4 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Maithili Square
Haveli · lapsed
Oct 2025Oct 2025
lapsed
Dec 2026Apr 2027
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Maithili Square
P52100031757 · Haveli
Ruko
Maithili Aroma
P52100049541 · Haveli
Pakka