BUILDER

Mestry Housing And Infrastructure

Type Firm / individualRERA projects 1Districts Ratnagiri
BUILDER THOK
Ruko
1 of 1projects with possession moved
12 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Tara Residency Phase -II
Ratnagiri · lapsed
Sept 2024Sept 2025
12 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Tara Residency Phase -II
P52800025384 · Ratnagiri
Ruko