0 of 19projects with possession moved
0 moaverage extension when late
0lapsed registrations
19MahaRERA projects
Delivery track record
Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Oct 2020Oct 2020
on time
Construction Of 432 EWS Houses Under Pmay Scheme At New Moradabad Scheme Sector 10A Pocket-2
Oct 2020Oct 2020Moradabad
on time
Construction Of 288 EWS Houses Under Pmay Scheme At New Moradabad Scheme Sector 10A Pocket-1
Oct 2020Oct 2020Moradabad
on time
Construction Of 144 EWS Houses Under Pmay (Urban) Scheme At Dhakka Gata NO. 271, 399, Moradabad
Jun 2021Jun 2021Moradabad
on time
Jun 2021Jun 2021
on time
Jun 2023Jun 2023
on time
Signals from filings & records
No approved insolvency matchIBBI
No IBBI announcement has been matched to this builder after review.
IBBI public announcements
Projects
112 EWS Houses At Sector-15a New Moradabad
UPRERAPRJ13004 · Moradabad
Group Housing At Kundanpur Dhakka Gata No 209
UPRERAPRJ12964 · Moradabad
32 Mmig Houses At Sector-15a New Moradabad
UPRERAPRJ13001 · Moradabad
176 LIG Houses At Sector-15a New Moradabad
UPRERAPRJ13005 · Moradabad
Group Housing At Kundanpur Dhakka Gata No 381 & 382
UPRERAPRJ12670 · Moradabad
48 MIG Houses At Gata No 387 Harthala (Ramganga Vihar)
UPRERAPRJ13007 · Moradabad
Group Housing At Dehri Mustakam
UPRERAPRJ12621 · Moradabad
Group Housing At Kundanpur Dhakka Gata No 402 & 413
UPRERAPRJ12668 · Moradabad
Construction Of 288 EWS Houses Under Pmay Scheme At Gata NO. 357 Shahpur Tigri, Moradabad
UPRERAPRJ15607 · Moradabad
Construction Of 432 EWS Houses Under Pmay Scheme At New Moradabad Scheme Sector 10A Pocket-2
UPRERAPRJ15605 · Moradabad
Construction Of 288 EWS Houses Under Pmay Scheme At New Moradabad Scheme Sector 10A Pocket-1
UPRERAPRJ15617 · Moradabad
Construction Of 144 EWS Houses Under Pmay (Urban) Scheme At Dhakka Gata NO. 271, 399, Moradabad
UPRERAPRJ419002 · Moradabad