BUILDER

Moraj Buildcon PVT LTD

Type CompanyRERA projects 2Districts Thane
BUILDER THOK
Dhyaan Do
1 of 2projects with possession moved
4 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Moraj Prive
Navi Mumbai (M Corp.) · lapsed
Dec 2024Dec 2024
lapsed
Apr 2030Aug 2030
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements