Moreshwar Developers

Type Firm / individualRERA projects 2Districts Pune, Thane
BUILDER THOK
Ruko
1 of 2projects with possession moved
23 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
May 2025Apr 2027
23 mo
19 East
Thane · lapsed
Dec 2025Dec 2025
lapsed

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Moreshwar Enclave
P52100055219 · Haveli
Ruko
19 East
P51700025055 · Thane
Ruko