BUILDER

Naiknavare Buildcon PVT LTD

Type CompanyRERA projects 10Districts Pune
BUILDER THOK
Ruko
2 of 3projects with possession moved
50 moaverage extension when late
1lapsed registrations
10MahaRERA projects · 7 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Naiknavare Kutumb Prime
Wadagaon (ct) · lapsed
Mar 2019Jun 2023
51 mo
Neelaya Project 2
Talegaon Dabhade (M Cl)
Jun 2022Jun 2022
not moved
7 Business Square
Pune (M Corp.)
Dec 2023Dec 2027
48 mo
7 more projects are being verified or have no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

3 of 10 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Naiknavare Kutumb Prime
P52100002518 · Wadagaon (ct)
Ruko
Neelaya Project 2
P52100021179 · Talegaon Dabhade (M Cl)
Ruko
7 Business Square
P52100022523 · Pune (M Corp.)
Ruko
Kutumb Prime
P52100003209 · Mawal
Not scored
Kutumb Prime
P52100002090 · Wadagaon (ct)
Not scored
Kutumb Prime
P52100002348 · Wadagaon (ct)
Not scored
Kutumb Bhoomi
P52100026636 · Wadagaon (ct)
Not scored
Kutumb Prime Project 6
P52100077735 · Mawal
Not scored
Neelaya Project 3
P52100030648 · Talegaon Dabhade (M Cl)
Not scored
Neelaya
P52100000013 · Talegaon Dabhade (M Cl)
Not scored