BUILDER

Navkar Groups Private Limited

Type CompanyRERA projects 3Districts Mumbai Suburban, Ratnagiri
BUILDER THOK
Ruko
2 of 3projects with possession moved
68 moaverage extension when late
2lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2018Apr 2028
112 mo
Navkar Heights
Borivali · lapsed
Dec 2021Dec 2023
24 mo
Navkar Mannat
Zadgaon Ct · lapsed
Dec 2022Dec 2022
lapsed

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Navkar Girija Sadan
P51800006112 · Borivali
Ruko
Navkar Heights
P51800004596 · Borivali
Ruko
Navkar Mannat
P52800022020 · Zadgaon Ct
Ruko