BUILDER

Nilesh Vishnu Patil

Type Firm / individualRERA projects 1Districts Raigarh
BUILDER THOK
Ruko
1 of 1projects with possession moved
28 moaverage extension when late
1lapsed registrations
1MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Kuber Avenue
Panvel · lapsed
Dec 2022Apr 2025
28 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Kuber Avenue
P52000026829 · Panvel
Ruko