Type Firm / individualRERA projects 4Districts Palghar
BUILDER THOK
Ruko
3 of 3projects with possession moved
43 moaverage extension when late
0lapsed registrations
4MahaRERA projects · 1 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2022Apr 2027
52 mo
Mar 2023Apr 2027
49 mo
Dec 2024Apr 2027
28 mo
1 more project is being verified or has no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

3 of 4 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Wollywood Phase II
P99000014632 · Gates Bk.
Ruko
Wollywood Phase III
P99000016446 · Gates Bk.
Ruko
Wollywood Phase IV
P99000016676 · Vada
Ruko
Wollywood Phase V
P99000053858 · Vada
Not scored