BUILDER

Oberoi Constructions Limited

Type CompanyRERA projects 4Districts Mumbai Suburban
BUILDER THOK
Ruko
2 of 3projects with possession moved
31 moaverage extension when late
1lapsed registrations
4MahaRERA projects · 1 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2022Aug 2024
20 mo
Eternia Towers A To D
Kurla · lapsed
Dec 2022May 2026
41 mo
Maxima
Andheri
Jun 2023Jun 2023
on time
Prisma
Andheri
——
—

Signals from filings & records

Verification in progressMahaRERA

3 of 4 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Enigma Towers A And B
P51800002656 · Kurla
Ruko
Eternia Towers A To D
P51800006141 · Kurla
Ruko
Maxima
P51800017154 · Andheri
Ruko
Prisma
P51800004199 · Andheri
Not scored