BUILDER

Om Sagar Developers

Type Firm / individualRERA projects 3Districts Pune
BUILDER THOK
Ruko
1 of 2projects with possession moved
12 moaverage extension when late
0lapsed registrations
3MahaRERA projects · 1 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Waters Edge Phase V
Pimpri Chinchawad (M Corp.)
Mar 2022Mar 2022
not moved
Waters Edge Phase Vi
Pimpri Chinchawad (M Corp.)
Sept 2022Sept 2023
12 mo
1 more project is being verified or has no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

2 of 3 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Waters Edge Phase V
P52100002038 · Pimpri Chinchawad (M Corp.)
Ruko
Waters Edge Phase Vi
P52100001427 · Pimpri Chinchawad (M Corp.)
Ruko
Waters Edge Phase IV
P52100001678 · Pimpri Chinchawad (M Corp.)
Not scored