BUILDER

Orbit Ventures Developers

Type Firm / individualRERA projects 2Districts Mumbai Suburban
BUILDER THOK
Ruko
2 of 2projects with possession moved
29 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Shikhar A
Andheri · lapsed
Dec 2019Dec 2021
24 mo
Shikhar B
Andheri
Dec 2024Oct 2027
34 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.