Pankaj Developers

Type Firm / individualRERA projects 7Districts Pune
BUILDER THOK
Dhyaan Do
4 of 6projects with possession moved
54 moaverage extension when late
0lapsed registrations
7MahaRERA projects · 1 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2019Apr 2028
100 mo
Oct 2021Apr 2027
66 mo
Dec 2025Dec 2027
24 mo
Dec 2025Dec 2027
24 mo
Dec 2026Dec 2026
not moved
Dec 2031Dec 2031
not moved
1 more project is being verified or has no declared dates yet.

Signals from filings & records

Verification in progressMahaRERA

6 of 7 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Pankaj Aasmaan Phase II
P52100005649 · Lahagaon
Ruko
Pankaj Aasmaan Phase III
P52100016512 · Haveli
Ruko
Pankaj Aasmaan Phase Vi
P52100023709 · Lohgaon
Ruko
Pankaj Aasmaan Phase IV
P52100023607 · Lohgaon
Ruko
Pankaj Aasmaan Phase V
P52100023613 · Lohgaon
Pakka
Pankaj Ekaant
PM1260002601964 · Haveli
Pakka
Pankaj Aasmaan Phase I
P52100009665 · Lahagaon
Not scored